I-77 Lane Closures Begin for $249M N.C. 150 Bridge Project in Mooresville

November 6, 2026
I-77 Lane Closures Begin for $249M N.C. 150 Bridge Project in Mooresville
  • Crews will begin temporary single-lane closures on Interstate 77 near the N.C. 150 exit 36 in Mooresville to build a new 10-lane bridge, including a safety barrier wall and new pavement markings.

  • Blythe Development, a Charlotte-based contractor, will install the safety barrier wall and add pavement markings during the closures, per a North Carolina Department of Transportation news release.

  • The NCDOT project will continue construction on a new N.C. 150 bridge over Interstate 77 in Mooresville, linking Iredell and Catawba counties.

  • The Lake Norman-area project aims to accommodate growing traffic and ease congestion, with work that began last year focusing on drainage, utilities and traffic signal improvements.

  • The overall 15-mile project is expected to be completed in 2030, according to the NCDOT project page.

  • Construction began last year with work on storm drainage, utilities and traffic signals, and bridge construction will occur in multiple phases while traffic remains on the existing N.C. 150 lanes.

  • Bridge construction will occur in multiple phases, with traffic maintained on the existing N.C. 150 lanes throughout the process.

  • Officials have not specified how long the temporary closures will last.

  • The closures are part of a $249 million project to improve the I-77 and N.C. 150 interchange and widen N.C. 150 from N.C. 16 in Catawba County to the U.S. 21/N.C. 150 interchange in Mooresville, in the Lake Norman area.

  • Traffic will shift from the median to the outside lanes once temporary barriers and markings are in place, as interior bridge bents are built.