GS Breaks Ground on South Korea’s First 2.4-Gigawatt AI Data Center
November 28, 2026
GS Group has begun construction in Donghae City, Gangwon State, on the first phase of a planned 2.4-gigawatt AI data-center complex—the first groundbreaking among South Korea’s “Three Mega-Projects for a Great Leap Forward.”
At the November 28 ceremony, attended by President Lee Jaemyung and about 270 officials, company representatives and local residents, Lee said South Korea must move quickly in the global AI race and pledged government support to make the country a leading AI nation.
The complex is planned in two 1.2-gigawatt phases, with the first 100-megawatt facility targeted for completion in the second quarter of 2028 and the full first phase expected to operate by 2029.
GS estimates the first phase will require 15 trillion won in investment and construction across both phases about 30 trillion won; including GPUs, memory and other AI equipment, the project’s total scale could reach 120 trillion won.
Construction began four months after a July 2026 memorandum of understanding, following accelerated completion of approvals that can typically take years, including power-system assessments, industrial-complex plan changes and building permits.
Donghae was selected for its East Coast power-generation capacity and the potential to use seawater for environmentally friendly cooling.
GS is working with LS Electric, POSCO, LG Uplus and Honeywell Technologies on equipment, design and operations, while also partnering with startups focused on power supply and server cooling.
GS plans to prioritize local residents for construction and service jobs, develop training courses with universities in Gangwon State and employ up to 1,000 direct and indirect operations staff once the facility is complete.
The company estimates the first phase could generate about 70,000 cumulative direct and indirect jobs during construction and plans to work with Donghae City on environmental and community concerns; following local feedback, the underground transmission route was changed to bypass the Bukpyeong five-day market.
GS and Donghae City have formed a mutual-development council to assess environmental and community impacts and explore ways to support local jobs and economic growth.
GS plans to use Donghae as a base for expanding its data-center business elsewhere, drawing on the group’s energy operations and considering other group-owned or suitable sites.
The project fits the government’s ambition to make South Korea an Asia-Pacific AI infrastructure hub by 2030, with a special AI data-center industry law due to take effect in March 2027 and plans for technology clusters to strengthen domestic capabilities.
Summary based on 7 sources
Get a daily email with more AI stories
Sources

CHOSUNBIZ • Nov 28, 2026
GS breaks ground on 1.2 GW AI data center in South Korea
The Asia Business Daily • Nov 28, 2026
Donghae Breaks Ground on Asia's Largest 2.4-GW AI Data Center... 'K-AI's Heart' Starts Beating - The Asia Business Daily