Judge Overturns Wind Energy Permitting Moratorium: Calls for Transparent, Reasoned Justification

December 9, 2025
Judge Overturns Wind Energy Permitting Moratorium: Calls for Transparent, Reasoned Justification
  • Reporting on the judgment date, December 9, 2025, with coverage by Law.com’s Alyssa Aquino.

  • Empire Wind continues toward a roughly two-year construction schedule with full operation planned by end of 2027, though the ruling affects broader permitting practices rather than this project alone.

  • The ruling is positioned within Maine’s broader energy strategy and regulatory landscape, without predicting outcomes beyond the court decision.

  • The decision could spur further lawsuits or appeals, but reinforces that a president’s directive alone cannot justify major permitting suspensions without a solid, reasoned record.

  • Judge Saris noted that the policy marked a break from decades of agency practice and that the administration failed to provide adequate justification for the shift.

  • A status conference is set for the following week to map next steps as parties await further guidance from Judge Saris.

  • The decision emphasizes that agencies cannot suspend permitting solely on a presidential directive and must provide a reasoned, transparent record as part of due process.

  • New York Attorney General Letitia James framed wind energy as beneficial to the environment, economy, and communities, and criticized the actions as reckless against clean energy efforts.

  • Even with the ruling, agencies may still deny permits or require lengthy reviews, meaning the industry could face limited immediate relief beyond a reassessment of procedures.

  • The court rejected narrowing relief to specific projects, ordering agencies to resume processing permits within a reasonable period and to conduct a comprehensive assessment.

  • A federal judge ruled against the administration’s moratorium on wind energy permitting, siding with more than a dozen states and a clean energy group that argued the pause was unlawful and lacked a solid, documented rationale.

  • Industry observers warn of ongoing legal and logistical uncertainty and stress the need to translate the ruling into concrete permit approvals and project progress.